Construction will continue throughout the downtown project area during the week of October 5. Underground utility work for the 2026 Downtown Reconstruction Project is underway complete. Crews continue to rebuild the streets and moving overhead electrical/cable service underground.
Planned work includes:
- Xcel Energy will bury electrical lines along Main Street East, working west from Budd Avenue continuing the week of October 5.
- Frontier & MediaCom will continue utility work during the week of October 5.
- Crews will continue to rebuild the downtown streets. Crews will continue to move east along Main Street and the side streets.
- It typically takes 1 day to rebuild 1 block length of street.
- Crews will pave the parking lot at Rainbow Park mid-October.
Residents and motorists should expect construction equipment, temporary access restrictions, and changing traffic patterns. Please use caution in work zones, follow posted signs, and allow extra travel time.
Schedules may change due to weather, site conditions, or other unexpected issues. Thank you for your patience and cooperation as crews complete these important improvements.
Library Access
As construction continues in the downtown project area, access to the Maple Plain Library is temporarily limited.
The only access to the library is by traveling south on Budd Avenue from Highway 12. There is no access to the library from the Main Street East and Budd Avenue intersection (traveling north on Budd Avenue).
Please follow posted detour signs and allow extra travel time when visiting the library.
Future Updates
For more information, click HERE.